Does the K2000 depend on the K1000?
We've been running both the K1k and K2k for 11 years. We're keeping the K2k for system deployment, but replacing the K1k. We're unsure if the pre\post scripts might need the K1000.
Could getting rid of the K1000 cause any issue for the K2000?
Thanks for any help or suggestions.
1 Comment
[ + ] Show comment
-
nope, each one is able to exist alone perfectly fine - Channeler 4 years ago
Answers (1)
Please log in to answer
Posted by:
Nico_K
4 years ago
both are integrated but don't depend on each other.
There may some tasks which depend on the SMA.
SOmething like: Collect the computername from the SMA or scripts which are starting actions on the SMA.
SO you should review all of your tasks here.